ProZ.com global directory of translation services
 The translation workplace
Ideas
KudoZ home » English to Czech » Engineering: Industrial

First Article Inspection

Czech translation: kontrola prvního kusu


Login or register (free and only takes a few minutes) to participate in this question.

You will also have access to many other tools and opportunities designed for those who have language-related jobs
(or are passionate about them). Participation is free and the site has a strict confidentiality policy.
19:59 Jul 12, 2009
English to Czech translations [PRO]
Bus/Financial - Engineering: Industrial / Contracts, GRLDs
English term or phrase: First Article Inspection
"All major project milestones should also include Quality Contract Review, Preliminary and Final Design Reviews, Type Testing, First Article Inspection, and Pre-Manufacturing Review."

"Všechny hlavní milníky projektu by měly také zahrnovat Smluvní přezkoumání kvality (???), Předběžné a závěrečné kontroly návrhu/designu (???), typové zkoušky/typování, ***Prvnotní kontrolu výrobku (???????) a Předvýrobní kontrolu/inspekci (???)."

I'd be grateful for your suggestions regarding expressions marked with (???), but for the time being, "First Article Inspection", which occurs several times throughout the particular document, is vital. Thanks for any help very very much!
petusek
Local time: 23:46
Czech translation:kontrola prvního kusu
Explanation:
FAI (First Article Inspection) :
Originally, FAI (First Article Inspection) just involved checking one component in the first batch. At present, FAI consists of the process monitoring of key characteristics. This is done in the FAI process to assure that parts can be manufactured continually, inexpensively, complying with the specification and with minimum disparity.
The FAI process consists of two discrete stages:
• First Article Inspection: The FAI is a complete, independent, and documented physical and functional inspection process to verify that prescribed production methods have produced a fully conforming item as specified.
• Component Proving
Selected response from:

Ivan Šimerka
Czech Republic
Local time: 23:46
Grading comment
Excellent! Thanks a lot! :-)
4 KudoZ points were awarded for this answer



Summary of answers provided
5 +5kontrola prvního kusuIvan Šimerka


  

Answers


18 mins   confidence: Answerer confidence 5/5 peer agreement (net): +5
first article inspection
kontrola prvního kusu


Explanation:
FAI (First Article Inspection) :
Originally, FAI (First Article Inspection) just involved checking one component in the first batch. At present, FAI consists of the process monitoring of key characteristics. This is done in the FAI process to assure that parts can be manufactured continually, inexpensively, complying with the specification and with minimum disparity.
The FAI process consists of two discrete stages:
• First Article Inspection: The FAI is a complete, independent, and documented physical and functional inspection process to verify that prescribed production methods have produced a fully conforming item as specified.
• Component Proving



    Reference: http://www.ucl.cz/download/pdf/PO_ST_21A.139_a_A_.pdf
Ivan Šimerka
Czech Republic
Local time: 23:46
Specializes in field
Native speaker of: Native in CzechCzech
PRO pts in category: 24
Grading comment
Excellent! Thanks a lot! :-)

Peer comments on this answer (and responses from the answerer)
agree  jankaisler
10 hrs

agree  srubkova
11 hrs

agree  Kateřina Suchánková
12 hrs

agree  Pavel Prudký
15 hrs

agree  Ivo Pajorek
2 days15 hrs
Login to enter a peer comment (or grade)




Return to KudoZ list


KudoZ™ translation help
The KudoZ network provides a framework for translators and others to assist each other with translations or explanations of terms and short phrases.



See also: