GLOSSARY ENTRY (DERIVED FROM QUESTION BELOW) | ||||||
---|---|---|---|---|---|---|
|
13:11 Dec 20, 2010 |
French to English translations [PRO] Geology | |||||||
---|---|---|---|---|---|---|---|
|
| ||||||
| Selected response from: B D Finch France Local time: 17:13 | ||||||
Grading comment
|
Summary of answers provided | ||||
---|---|---|---|---|
4 +2 | drilling runs |
| ||
3 | borehole stage |
|
Summary of reference entries provided | |||
---|---|---|---|
GEOTECHNICAL PRODUCTS |
|
Discussion entries: 1 | |
---|---|
borehole stage Explanation: "Stage" is said of a length of borehole in relation to pressure testing or grouting of cracked rock and may well be applied to successive phases of drilling also. |
| |
Login to enter a peer comment (or grade) |
drilling runs Explanation: Compare: "Every minute during the drilling process, the accelerometers sense the ‘low side’ of the core tube and records the position in the memory. On completion of the drilling run, the tool is returned to the surface and the driller enters the time at which the core ..." and "Chaque minute durant le processus de forage, les accéléromètres sentent le ‘côté bas’ du tube de carotte et enregistrent la position dans la mémoire. À la fin de l’exécution de la passe de forage, l’outil est retourné à la surface et le foreur entre ..." -------------------------------------------------- Note added at 1 hr (2010-12-20 14:41:42 GMT) -------------------------------------------------- http://www.reflexinstruments.com/docman/brochure-reflex-act-... for the French version -------------------------------------------------- Note added at 3 hrs (2010-12-20 17:06:11 GMT) -------------------------------------------------- There could be a number of drilling runs in a phase. E.g. based upon the analysis of cores obtained from drilling runs in the initial sampling phase, there could be a decision to carry out more detailed investigative work involving further drilling runs for core sampling to particular sections of the site. Reference: http://www.google.fr/url?q=http://www.reflexinstruments.com/... Reference: http://www.google.fr/url?sa=t&source=web&cd=1&ved=0CBsQFjAA&... |
| |||||||||
|
1 hr |
Reference: GEOTECHNICAL PRODUCTS Reference information: http://www.datc-group.com/upload/catalogue/Partie2.pdf Longueur maximale de la passe de forage fait avant introduction de la sonde pressiomètrique Maximum drilling lengths cut prior to the introduction of the pressiometric drill Les longueurs maximales de forage pressiomètrique à réaliser avant l’introduction de la sonde dépendent des propriétés des terrains, de l’existence d’une nappe et de la présence ou non d’un tubage. La longueur maximale de forage fait à l’avance doit respecter les règles regroupées dans le tableau ci-dessous. The maximum drilling lengths to be cut prior to the introduction of the drill depend on the soil properties, the existence of a layer and the presence or otherwise of a tubing. The maximum length of prior drilling must comply with the rules set out below. |
| |
Login to enter a peer comment (or grade) |
Login or register (free and only takes a few minutes) to participate in this question.
You will also have access to many other tools and opportunities designed for those who have language-related jobs (or are passionate about them). Participation is free and the site has a strict confidentiality policy.