Glossary entry (derived from question below)
Jan 30, 2003 08:18
21 yrs ago
14 viewers *
Italian term
pozzetto
Italian to English
Tech/Engineering
descrizione di un impianto per trattamento rifiuti
Pozzetto laterale per alloggiamento valvolame
Proposed translations
(English)
4 +3 | well | Sarah Ponting |
Proposed translations
+3
5 mins
Selected
well
in questo caso "valve well"
--------------------------------------------------
Note added at 2003-01-30 08:25:48 (GMT)
--------------------------------------------------
sometimes also translated as sump
--------------------------------------------------
Note added at 2003-01-30 08:29:21 (GMT)
--------------------------------------------------
\"The valves in these and several other installations were oriented in themanner of the conventional tainter gate, that is, with the trunnionsdownstream of the skin plate causing the convex surface of the skinplate to face the flow and seal along the upstream end of the valve well.\"
www.usace.army.mil/inet/usace-docs/ eng-manuals/em1110-2-1610/c-1.pdf
\"The project consists of removing the existing approximately 225 linear feet of double wall diesel fuel line from the fuel sensor and valve sump at the head of Pier #2 to the dispenser on Pier #2 to include removal of sump and valve and piping supports.\"
http://www.fbodaily.com/cbd/archive/1999/10(October)/22-Oct-...
--------------------------------------------------
Note added at 2003-01-30 08:25:48 (GMT)
--------------------------------------------------
sometimes also translated as sump
--------------------------------------------------
Note added at 2003-01-30 08:29:21 (GMT)
--------------------------------------------------
\"The valves in these and several other installations were oriented in themanner of the conventional tainter gate, that is, with the trunnionsdownstream of the skin plate causing the convex surface of the skinplate to face the flow and seal along the upstream end of the valve well.\"
www.usace.army.mil/inet/usace-docs/ eng-manuals/em1110-2-1610/c-1.pdf
\"The project consists of removing the existing approximately 225 linear feet of double wall diesel fuel line from the fuel sensor and valve sump at the head of Pier #2 to the dispenser on Pier #2 to include removal of sump and valve and piping supports.\"
http://www.fbodaily.com/cbd/archive/1999/10(October)/22-Oct-...
Peer comment(s):
agree |
awilliams
: hi Sarah
1 min
|
Good morning, Amy! Thanks.
|
|
agree |
Peter Leistra
4 mins
|
thanks, Peter
|
|
agree |
Louise Norman
8 mins
|
thanks, Louise
|
4 KudoZ points awarded for this answer.
Comment: "Thanks! Regards, Giorgia"