5 | riser shaft |
| ||
3 +1 | wiring/cabling chute |
| ||
4 | crawl space / conduit |
| ||
3 | (vertical) maintenance shaft |
| ||
3 | utilities shaft |
|
(vertical) maintenance shaft Explanation: would be my solution here...it's what these things are called for the sewage system, for example... |
| |
Login to enter a peer comment (or grade) |
wiring/cabling chute Explanation: Based on the German description below, I think cabling or wiring chute or duct would be appropriate here. 8.3.4 ERSCHLIEßUNG Die Erschließung eines Sekundärbereiches kann entsprechend den Anforderungen als ringförmige oder sternförmige Sekundärverkabelung ausgeführt werden. Bei der Planung der Etagenverteiler in Neubauten sollten sämtliche Verteiler und der dazugehörende Steigeschacht übereinander liegen. Idealerweise sollte der Steigeschacht innerhalb des Verteilerraumes geführt werden. Bei der Planung der Steigeschächte ist darauf zu achten, daß diese nach Fertigstellung ohne großen Aufwand für eventuell anstehenden Nachverkabelungen erreichbar sind. Im Steigebereich sind Kabelleitern mit einem Abstand von Sprosse zu Sprosse von ca. 30-40 cm einzuplanen. Bei der Befestigung der Kabel (Glasfaser und Kupfer) ist darauf zu achten, daß die Kabelschellen nur leicht angezogen werden um die Kabel nicht zu beschädigen. Das Befestigen der Kabel mittels Kabelbinder oder Drähten ist nicht zulässig. -------------------------------------------------- Note added at 2002-08-15 20:45:33 (GMT) -------------------------------------------------- Steigleitung Der Steigleitungsbereich gehört zur Gebäudeverkabelung und wird in der strukturierten Verkabelung mit Lichtwellenleitern oder optional mit TP-Kabeln ausgeführt. Es handelt sich um ein Installationssegment zur Verbindung des Gebäudeverteilers mit den Etagenverteilern. Im Verkabelungsstandard ist dieser Bereich mit einer maximalen Länge von 500 Metern spezifiziert. http://w3.siemens.de/solutionprovider/_online_lexikon/ Reference: http://www.greenseagull.com/GS/2002/02feb/01.htm Reference: http://www.stl-online.de/s08.htm |
| |
Grading comment
| ||
Login to enter a peer comment (or grade) |
crawl space / conduit Explanation: a space between the ground and the first floor of a structure where repair of utilities under the house may be made by a person crawling through the shallow space An artificial channel such as a pipe used for conveying or protecting water, wires or other materials From Real Estate Dictionary |
| |
Login to enter a peer comment (or grade) |
utilities shaft Explanation: Assuming the shaft is not only used for cables, but also for water, gas, etc. |
| |
Login to enter a peer comment (or grade) |
riser shaft Explanation: I frequently used this term in my arch/constr translations. This would provide accommodation of both electrical installations (wiring/cabling) and utilities such as water and gas. Actually, "risers" are "Steigleitungen". -------------------------------------------------- Note added at 2002-08-16 09:59:19 (GMT) -------------------------------------------------- On second thought, I believe that the \"Steigeschächte\" mentioned in the source text primarily refer to pipework (risers) e.g. for water and gas supply, and have less to do with power lines/cables. Question of further context though... |
| |
Login to enter a peer comment (or grade) |
Login or register (free and only takes a few minutes) to participate in this question.
You will also have access to many other tools and opportunities designed for those who have language-related jobs (or are passionate about them). Participation is free and the site has a strict confidentiality policy.