4 +5 | Actual=Target |
| ||
4 | actual state/value = set state/value |
| ||
4 | As is = To be |
| ||
4 | stock on hand = target inventory |
|
Actual=Target Explanation: Ist-Zustand = Soll-Zustand, d.h. die Vorgaben wurden erreicht |
| |